August 2011 – Leslie Rd. Phase II
| Owner: |
City of Richland |
Contract Amount: |
$ 1,052,000 |
| Project Manager: |
Tyler Tapani |
| Superintendent: |
Jonah Sproul |
|
|
| Description: |
Installation of new roundabout in the intersection of Clearwater Ave. and Leslie Road. Removing existing asphalt, utilities and placing structural fill for the additional width needed. Remove and replace existing concrete curb and sidewalk. |
| Subcontractors: |
A&B Asphalt, Granite Construction, West Coast Road Recycling, Baisch Vegetation Management, North Country Construction, Sierra Electric, Quality Sign Service |